  1. September 26, 2026

    Second Outage In 3 Years At Brookfield Dam May Have Killed Thousands Of Fish

    Great Lakes Hydro America, Brookfield's operator for the project, said its automatic minimum-flow equipment functioned properly and that regulators were alerted, while Maine wildlife officials said they are looking into how long the event lasted and what it did to the fish population.

    Dam operator
    Great Lakes Hydro America (Brookfield Renewable)
    Flow drop
    About 2,400 cfs to about 450 cfs
    Preliminary death estimate
    3,800 to 7,700 juvenile salmon